Job Name: Maplewood Development
Location: Nashua, New Hampshire
Completion: Fall 2003

  • Property Area: Phase 4 and Phase 5A 24 Acres
  • Buildable lots: 65 house lots [249 lots total for Phases 1-6]
  • Driveway Area: 5000 linear feet of road
  • Earthwork strip, grubbing, cuts, fill, and borrow.
  • Yardage: 60,000 cubic yards of cuts and fill. 90% of the material was ledge and had to be blasted.

Scope of work

  • Blasting 90 % of the site
  • Road/street construction 5,000 linear feet
  • Electric 5,000 linear feet underground
  • Telephone 5,000 linear feet underground
  • 8" Sewer main 5,000 linear feet underground
  • CTV conduit 5,000 linear feet underground
  • Drain Pipe 5,000 linear feet Reinforce concrete pipe size ranges from 12" to 42" underground
  • Water main 5,000 linear feet 8" to 12" underground
  • Underground utilities, water and sewer service hook-ups for 65 house lots

Purpose of project

Development of Phase 4 and 5A of a 6 phase project in Nashua. These are all residential lots with approximately 10,000 to 15,000 sq ft of property.  

      

Significance:

Site excavation is a creative process, even after 20 years, unusual and unpredictable events happen. Every project has its own unique designs, and its unaccepted glitches that need to be considered when executing the scope of work.

The Maplewood Development Project had its share of unique challenges.  The entire site was solid ledge. The bedrock needed to be blasted and then screened for suitable backfill material once the underground utilities were laid.

Before the new city road was paved all of the disturbed areas and future house lots needed to be backfilled to it relative grades.